Close-outs

Close-out records what happened after work ends. Ending or cancelling work and submitting its close-out are separate actions: a saved draft is not a submitted report.

Close-out uses update work activities permission. Head Office and Project Supervisors can complete it; Subcontractor Supervisors can complete their own company’s close-outs. Users cannot submit. After submission, only Head Office or a Project Supervisor can correct it.

Close-outs list showing finished activities awaiting answersClose-outs list showing finished activities awaiting answers
Follow up finished work until its close-out is submitted, not just saved as a draft.
  1. Open the finished activity, or find it in Close-outs, and choose Start Close-Out. If a draft exists, choose Resume Close-Out instead.
  2. Record the outcome and whether the work was completed. For Example Project’s cable installation, report what Example Electrical actually achieved across Loading Dock and Plant Room.
  3. Follow Next through the questions shown. Depending on the outcome, these cover delay reasons, lost time and causes, zone fit, other activities affecting the job, access, resources, materials and safety events. Answer the follow-ups rather than adding everything only to a general comment.
  4. If you need to check details with the crew, select Save Draft. Reopen with Resume Close-Out to continue from the saved answers. Do not rely on leaving the page to save changes.
  5. Review the answers and choose Submit Close-Out. Correct any validation message, including required explanations for Other answers, then submit again.
  6. Look for Close-Out Submitted and confirm the activity is no longer awaiting submission.

Submitting does not restart work or reserve zones. The outcome answers inform metrics, so record an incomplete or delayed outcome honestly rather than choosing a clean result to finish the form sooner.

If ToolboxFM recorded a final extension, close-out shows the allocated start, allocated finish and when the extension ended. Times use the project’s timezone. A shared date is shown when all three times fall on the same day; otherwise each marker includes its date.

Answer Did the work finish on time or go into extension?:

  • Finished on time: choose this if the work finished within the latest allocated window but somebody recorded End late. You do not need an exact finish time.
  • Went into extension: keep the recorded overrun, or enter Actual finish (optional) if work finished late but before End was recorded. Use project time.

The correction affects extension metrics only when you submit, not when you save a draft. It applies only to the final extension; earlier extensions are kept. ToolboxFM retains the original End record and an audit trail of corrections. If no final extension was recorded, this question is not shown.

  1. If you are a Subcontractor Supervisor, ask Head Office or the Project Supervisor for a correction; you cannot submit a second version yourself.
  2. As an authorised reviewer, open the submitted close-out and select Edit Close-Out.
  3. Correct the answers and choose Save Changes, then check the updated report.

The original submitter and submission time are retained. The first filing and later corrections appear separately in the Project Diary, with an audit trail of changes.

Check that you opened the correct activity and company and that work has ended. If another person has already submitted, refresh before trying again. Missing required answers can be kept in a draft while you obtain the facts; submission needs the answers for the branch you followed. For access restrictions, contact Head Office and see Trial and upgrading.