Managing work
Who can act
Section titled “Who can act”Head Office, Project Supervisors and Subcontractor Supervisors have update work activities and cancel work activities permissions. A Subcontractor Supervisor can act only on their own company’s activities, even when they can see other work. Users cannot take these actions. Your authority must apply to the activity’s project.
For Example Electrical’s cable installation, open the activity and check that both Loading Dock and Plant Room, its approval and its time window are correct before taking an action.
Start approved work
Section titled “Start approved work”Approved scheduled work activates automatically when its start arrives while its finish is still in the future. Activation is not a substitute for your project’s checks before work begins.
- Open the approved activity.
- If it is still Scheduled and its finish has not passed, you can choose Start. The button can appear before the booked start; do not use it as a way to obtain a different booking window.
- Check that the lifecycle now says Active. Start does not approve pending or rejected work.
If the finish has passed, the page does not offer Start. Use the overdue recovery below. If automatic activation has already occurred, there is no need to start it again.
Pause and resume an interruption
Section titled “Pause and resume an interruption”- On an active, unpaused activity, choose Pause.
- Select the main reason. For Weather, you can also select Heat, Rain, Wind or Snow. Add optional detail in What is the issue? For other reasons, you can also record Discussion / Action and What is the outcome? Each text field allows up to 500 characters. Confirm the pause when ready; none of these extra details are required.
- Check the paused state. The activity remains Active and retains its linked zone bookings; pausing does not make Loading Dock or Plant Room available to another booking.
- When ready to continue, choose Resume and check that the paused indicator clears.
Pause history keeps the selected weather type and any details you recorded.
You can end paused work without resuming it first. If a button disappears, refresh the activity and check whether someone else has already paused, resumed or ended it.
Recover overdue work
Section titled “Recover overdue work”Passing Finish does not end an activity. Overdue can mean work ran on, or approved scheduled work never activated before its window expired. Check with the crew rather than assuming either outcome.
- Open the overdue activity from Today or Work activities.
- If more time is needed, choose Extend and enter a new finish in the future, after the start.
- Save and check the revised finish. All affected zones are checked for clashes over the revised window. If another approved booking clashes, coordinate with its supervisor and agree an available window; extension does not override it.
- If approved scheduled work was stranded, extending its finish into the future lets automatic activation pick it up. Check the activity state afterwards.
Extension history remains available for reporting. If work is finished, use End Activity instead of extending merely to clear an attention label.
End finished work or cancel work that will not start
Section titled “End finished work or cancel work that will not start”End Activity marks work completed. Cancel marks scheduled work cancelled. They are not synonyms.
- For active work (including paused work), choose End Activity — End on small screens. Approved scheduled work whose finish has passed can also be ended.
- Check for Completed. The activity no longer holds its zones and a close-out is requested afterwards; answering it is not a prerequisite to ending the activity.
- Follow Close-outs to record what actually happened.
For work that has not started:
- While it is Scheduled, choose Cancel.
- Select a cancellation reason, add relevant detail and confirm.
- Check for Cancelled. Any zone booking is released. Once work is active, use End Activity instead.
Missing or unavailable actions
Section titled “Missing or unavailable actions”Check approval, lifecycle, finish time, project and company before escalating to a Project Supervisor. Restricted projects can hide Start and Resume while still allowing closure actions such as Pause, End and Cancel; do not assume every write is disabled. Ask Head Office about access and see Trial and upgrading.
For state definitions, see Work activity lifecycle.
