Your first day

First accept your invitation and sign in to the correct workspace and project. Your role applies in that context: being a Project Supervisor on one project does not make you a supervisor on another.

Our worked example uses fictional demonstration data: Example Project, Example Electrical and a Cable installation activity affecting the example physical areas Loading Dock and Plant Room. Use your own project’s names and work. One activity can use both zones; each zone’s booking still needs to be free of overlapping approved work.

You can administer the organisation and see all its projects.

  1. Follow Set up your organisation through approval of the example activity, not just creation of the request.
  2. Confirm the Project Supervisor and Example Electrical’s supervisor have accepted and can find Example Project.
  3. Use Today to check the plan, or hand daily coordination to the Project Supervisor. Head Office can also review and approve work.

For later changes, use Users and roles. Commercial arrangements and expiry are in Trial and ongoing access.

You manage work and approvals on your assigned project, and can manage its zones, subcontractors and project access. Creating projects or granting Head Office authority requires Head Office.

  1. Open Today for the correct project and date. Review the work and needs-attention items.
  2. Open pending Cable installation and check both Loading Dock and Plant Room, the company, window and safety answers. Follow Approving work to approve, reject or resolve a clash.
  3. Use Manage work for live changes and Close-outs to review how work finished and make authorised corrections.

Subcontractor Supervisor: request and run your crew’s work

Section titled “Subcontractor Supervisor: request and run your crew’s work”

You can request work and manage your own company’s activities, but cannot approve them. Your company assignment matters as well as your role; ask the Project Supervisor if it is missing or wrong.

  1. Follow Request work to submit Cable installation for Example Electrical, selecting both affected zones and the agreed window.
  2. Check its approval result before treating the slot as booked. Ask the Project Supervisor to review it. A pending request does not hold a zone.
  3. Follow Manage work for starting, pausing, resuming, extending or ending your company’s activity when available. Pausing is not a way to release the zones.
  4. Finish with Close-outs. Passing the planned finish time is not the same as ending the work.

The User role is a read-oriented project role, not a booking or approval role.

  1. Open Exclusion zones or Work activities and inspect the details you can view. The User role does not include the signed-in Today board.
  2. Check the work window and responsible people before coordinating with your supervisor. A public QR page is another way to view published project or zone information; it is not project membership.
  3. Ask your Subcontractor Supervisor to request or change your crew’s work, or your Project Supervisor about the overall plan. You cannot create or approve activities with the User role.

Check the workspace, project, role, company and activity state before assuming there is a fault. Read-only project access can also disable normal work. Use Troubleshooting and ask your Project Supervisor or Head Office to check your access rather than borrowing an account.